The latest update as of July 31st:
Concrete works - Completion of Stage 1: Pour of concrete basketball courts, footpaths and concrete channels
Completion of Stage 2: Pour of the concrete Tennis Court
Fencing installed around Tennis Court
Line marking completed on Tennis court and Basketball court
Installation of Tennis court net
Over the next two weeks:
Basketball hoop to be installed - scheduled for Monday, 3rd August 2026
U-Bars to be installed at road entrance on the west side - scheduled for Monday, 3rd August 2026
Remaining ACO drain grates to be installed - estimated 2-3 weeks